PECO is performing work in Huntingdon Pike and Byberry Road
Posted on 07/24/2026
PECO is performing work on Huntingdon Pike and Byberry road. Please allow for extra travel time through these areas.
Huntingdon Pike from Red Lion Road to Alden Road
updated 7/24/26:
When: Starting 8/10/26
What time: Between Red Lion Road and Buck Road will be completed during night hours 8pm-5am Monday-Thursday. From Buck Road to Alden Road will be completed during the day from 7am-3pm Monday- Friday
Byberry Road from Huntingdon Pike to Larch Road
updated 7/24/26:
When: Starting 8/10/26
What Time: 9am-3:30pm Monday-Friday
Byberry Road from Creek Road to Paper Mill Road
updated 7/24/26
Crews will be working 9am-3pm M-F
Traffic control operation are in place with local and emergency access
updated 5/4/26
PECO will be starting construction on Wednesday, May 27 for gas main replacement on Byberry Road (from Creek to Paper Mill). Traffic control will be in place from 7 am to 3 pm. Please allow extra time for travel through this area.
Project is expected to complete in Early September.